Rack battery comms fault with the inverter: what to check first?

Start with the communication path, not the battery cells. Most of these faults come from one of four things: the cable is in the wrong port, the pinout doesn't match, the protocol

Rack battery comms fault with the inverter: what to check first?

TalkOctober 22, 2026Redway Tech Editorial TeamTopic: BMS, CAN & Charger Integration
Buyer question / scenario

An installation company has started fitting 51.2V LiFePO4 rack modules from a new supplier. On the first sites the DC cables are fine and the battery powers on, but the hybrid inverter shows a BMS communication alarm and no state of charge. The company wants a checklist before rolling out to more sites.

Main answer

Start with the communication path, not the battery cells. Most of these faults come from one of four things: the cable is in the wrong port, the pinout doesn’t match, the protocol selected on the inverter doesn’t match the battery, or the master battery’s address or DIP setting is wrong. Check those in order before suspecting hardware.

Why it matters

With closed-loop communication, the inverter takes its charge and discharge limits and its state of charge from the BMS. Without it, the inverter may stop charging, raise an alarm, or fall back to voltage-only control. Redway’s PM-LV51200-5U and PM-LV51150-4U list RS485 and CAN-bus. Inverters named as compatible include Deye, Victron, GoodWe, Sol-Ark, SRNE, Solis, SAJ, Growatt, Luxpower, Voltronic, SMA and FOX.

Step-by-step check

  1. Port: confirm the cable runs from the battery’s designated inverter port (CAN or RS485) to the inverter’s BMS port, not to a monitoring or meter port.
  2. Pinout: RJ45 pin assignments differ between brands. Many inverters use a combined BMS port with CAN on one pair and RS485 on another. Compare both manuals and use the supplied or specified cable. Don’t assume a standard network cable will work.
  3. Protocol: select the matching battery protocol or brand setting on the inverter, and set the battery side to match if its protocol is selectable.
  4. Address: in a stack, set the module connected to the inverter as master, following the battery manual, and give the others unique addresses.
  5. Restart order: after changing DIP switches, power-cycle the battery so it reads the new address, then restart the inverter.
  6. Verify: the inverter should now show state of charge, cell or BMS data and charge limits.

Conditions and limits

Compatibility can depend on inverter firmware and BMS firmware versions. A brand appearing on a compatibility list doesn’t guarantee every model and firmware combination. Redway specifies a JBD BMS on these modules, but the protocol table for each inverter isn’t published on the product pages. Get it from Redway support for your inverter model.

Before rolling out across sites

Ask the supplier for the protocol table, cable pinout and DIP settings for each inverter model you install, and add them to your commissioning sheet. Redway’s rack module pages list RS485 and CAN-bus and name compatible inverter brands, but the per-inverter protocol table isn’t published on the pages, so request it in writing for your models and firmware.

Risk limits

Don’t run the system in lithium mode with high charge currents while communication is down unless the inverter’s voltage limits have been set conservatively to the battery datasheet values (58.4V maximum charge, 40V cut-off on these models). Turn off DC breakers before re-terminating cables. Our battery–inverter compatibility guide has more background.

Additional perspectives

Installer / integrator perspective

Standardise one pre-made communication cable per inverter brand and label it, rather than crimping on site. Photograph both ends at commissioning. Most repeat call-outs come from a cable that was right on one inverter brand and moved to another.

Redway Tech Editorial Team – Installer / integrator perspective

Distributor perspective

If you stock rack batteries for several installer customers, keep a compatibility sheet by inverter model and firmware, with the date each pairing was confirmed. Share it with installers and update it when inverter makers release firmware. It cuts support calls more than any single product change.

Redway Tech Editorial Team – Distributor perspective

Procurement perspective

Put the inverter models, firmware versions and required monitoring (SNMP, Bluetooth or WiFi, offered as upgrades on some Redway modules) in the RFQ, and ask for the communication cable to be included in the bill of materials. Redway lists up to 16 modules in parallel on the PM-LV series, so state your largest planned stack too.

Redway Tech Editorial Team – Procurement perspective

Specifications are taken from Redway product pages as of October 2026. Where a figure isn’t published, this article says so. Confirm current specifications for your model with Redway before ordering. This article is general guidance, not a site-specific engineering assessment.